Alterations In Simonswyk

Initially the brief for this project was for an alteration to a 1950’s spec house. However, it ended up being a for a semi-demolition and rebuild. Then, despite the 12 days of delay due to an unusually rainy winter, plus the unforeseen remedial work which included the replacement of all the existing surface beds, and the decision to plaster the bagged internal walls, the construction period end up just two weeks longer onto which was already a tight schedule. I think we successfully adapted to the all the changing aspects which arose.